Video Spotlight: A Boiler Room Transformation

  • 1 day ago
  • 2 min read

We've added a short before-and-after walkthrough of the Holiday Inn San Jose Silicon Valley boiler and maintenance room transformation. See the original case study here ►

The video begins with a silent 360-degree view of the original space, showcasing the existing 3-million BTU natural gas boiler system and 240 gallons of storage that previously served the hotel's hot water needs. The walkthrough then transitions to the completed installation, highlighting sixteen A. O. Smith CAHP-120 heat pump water heaters, expanded storage capacity, customized air circulation ductwork, and the mechanical room's transformation into a modern electrified hot water plant.

As the camera moves through the completed installation, viewers will see key project features identified throughout the video, including:


Heat Pump Water Heater Electrification

Converting a natural gas boiler system to electric heat pump water heaters


Existing Boiler System

  • 3 Million BTU

  • 240 Gallon Storage


HPWH System

  • 16 A.O. Smith CAHP-120

  • 220 Gallons Additional Storage

  • Customized Air Circulation

Switching to the new array reduces your peak input capacity by 1,766,016 BTU/HR, dropping from 3 million BTU/HR down to a maximum of 1,193,984 BTU/HR. However, it cuts your peak demand from an 867.28 kW gas energy equivalent to just 134.4 kW while ensuring that if a single unit fails, the remaining 15 seamlessly absorb the load without guests and the hotel staff ever losing hot water.


Project Highlights

  • Installation: 10 Days

  • Electricity Downtime: 2 Hours

  • Hot Water Downtime: Less Than 8 Hours


The contrast between the original mechanical room and the completed system offers a clear visual representation of what's possible when thoughtful engineering, coordinated plumbing and electrical installation, careful project management, and innovative planning come together. Beyond showcasing new equipment, the video demonstrates how a complex hospitality facility successfully modernized critical infrastructure while remaining operational and minimizing disruption to guests.


Watch the transformation https://youtu.be/lJJiav6iNds





 
 
 

Comments


Most Recent
APS_LOGO2.png

info@americanpowersolutions.com

8am - 5pm PST​​​

Tel : (714) 626-0300

Fax : (714) 626-0200 

14355 Industry Circle La Mirada, CA 90638

© 2026 by American Power Solutions

bottom of page